Project Aurora · PROJECT EXECUTION MAP

Build the visible factory

attention38% · 40/104 ptsSprint 08 · 6d left
7 events · fixture stream
Done11tasks
Active11in flight
Not started3tasks
Waiting8started, deps open

Milestones

planned → forecast
M1 Foundation readySSO, backup restore rehearsal, worker without production network
01 Nov → 29 Novat-risk · 35%tasks 0/1
POC board readyTask goes backlog → sprint → agent → status change → dependency → approval gate
15 Nov → 08 Novon-track · 75%tasks 7/7
M2 Safe executionTool allowlist, worktree isolation, audit event and kill switch
15 Nov → 06 Decat-risk · 30%tasks 0/1
M3 End to endOne task from intake to QC and approval on the dashboard
13 Dec → 20 Decat-risk · 40%tasks 0/2

Risks

4 open
high
Platform milestones M1/M2 have no implementation yetStart Control API contract spike (ASF-032) in Sprint 09 · PM · due 08 Nov
medium
Public routes may still bundle Three.js (AC17 unverified)Add bundle/network assertion to the E2E suite · DEV · due 15 Nov
medium
3D world has no automated regression or low-device modeTeardown/memory test and reduced-quality tier · QC · due 22 Nov
low
Fixture plan drifts from the status documentpnpm check:plan-sync runs with every batch · GUARDIAN · due 31 Oct

Plan versus actual

variance against planned end
TaskRefStatusPlannedActualVariance
ASF-001 Nuxt app shell and navigationVF-W1-01Done19 Oct – 25 Oct25 Oct – 25 OctOn time
ASF-002 Cozy V3 tokens with contrast audit and visual regressionVF-W1-02Done19 Oct – 25 Oct25 Oct – 25 OctOn time
ASF-003 Project switcher and component catalogVF-W1-03Done19 Oct – 25 Oct25 Oct – 25 OctOn time
ASF-041 Route map and layoutsWEB-01In progress19 Oct – 25 Oct25 Oct4d overdue
ASF-010 Product backlog CRUD and item inspectorVF-W2-01Done26 Oct – 01 Nov25 Oct – 25 Oct7d ahead
ASF-042 Route chunks and render rulesWEB-02In progress26 Oct – 01 Nov25 OctOpen
ASF-043 Public shell and Cozy componentsWEB-03In progress26 Oct – 01 Nov25 OctOpen
ASF-044 Nuxt Content blogWEB-04Done26 Oct – 01 Nov25 Oct – 25 Oct7d ahead
ASF-012 Active sprint board with rulesVF-W3-01Done02 Nov – 08 Nov25 Oct – 25 Oct14d ahead
ASF-040 Public shell and blogVF-W2-02In progress26 Oct – 08 Nov25 OctOpen
ASF-046 Services, Work and Contact pagesWEB-06In progress02 Nov – 08 Nov25 OctOpen
ASF-020 Execution contract: milestones, risks and eventsVF-W4-01Done09 Nov – 15 Nov25 Oct – 25 Oct21d ahead
ASF-021 Timeline with milestones and plan versus actualVF-W4-01Done09 Nov – 15 Nov25 Oct – 25 Oct21d ahead
ASF-022 Dependency DAG with critical pathVF-W4-01Done09 Nov – 15 Nov25 Oct – 25 Oct21d ahead
ASF-023 Agent lanes and activity streamVF-W4-01Done09 Nov – 15 Nov25 Oct – 25 Oct21d ahead
ASF-024 Shared task selection via URL across viewsVF-W4-01Done09 Nov – 15 Nov25 Oct – 25 Oct21d ahead
ASF-045 World-to-page transitionsWEB-05In progress09 Nov – 15 Nov25 OctOpen
ASF-047 WebGL lifecycle and performanceWEB-07In progress09 Nov – 15 Nov25 OctOpen
ASF-048 SEO, accessibility and analyticsWEB-08In progress09 Nov – 15 Nov25 OctOpen
ASF-030 Three.js Home World with data adapterVF-W5-01In progress16 Nov – 22 Nov25 OctOpen
ASF-031 3D ↔ route navigationVF-W5-02In progress16 Nov – 22 Nov25 OctOpen
ASF-049 Cross-route regression suiteWEB-09In progress16 Nov – 22 Nov25 OctOpen
ASF-032 Control API and PostgreSQL adapterVF-W6-01Refinement23 Nov – 29 Nov—Open
ASF-033 Claude Code CLI worker and RufloVF-W7-01Inbox30 Nov – 06 Dec—Open
ASF-034 QC, reports and hardeningVF-W8-01Inbox07 Dec – 13 Dec—Open

Activity

  1. movedProject Execution Map shipped (timeline, DAG, lanes, activity)
  2. blockedM1 Foundation forecast slips: no SSO or worker isolation yet
  3. movedSprint board rules and 13 E2E tests pass
  4. movedBacklog shares one repository with the sprint board
  5. movedComponent catalog and project switcher shipped
  6. movedApp shell, Home World and blog vertical slice shipped
  7. plannedRoadmap and visual-first plan accepted